1. Select the project you want to change the project start date in the
Project Workspace.
2. Select View, Show on Bottom, Project Details…
3. Click on the Dates tab: change the dates both in the
Planned Start and Data Date fields.

4. Open this project by right-clicking it in the Project workspace
and then select Open Project

5. Press F9 and check the date in the Current Data
Date
field; make sure that the data date is the one just you have
changed.

6. Click on the Schedule button.

10 comments:

Ammar Bukhari said...

That really helped :-)
thank You!

Ammar Bukhari said...

Thank you!
That really helped :-)

venkat said...

Thanks, It helped me

Unknown said...

Thanks , it is really helpful

Unknown said...

Thanks a lot - it is really helpful

Unknown said...

Good Explanation. It is helpful

Unknown said...

thanx a lot.i was tensed.its cleared

Elizabeth J. Neal said...

thank you for your interesting infomation. TrainingRoom SG

Unknown said...

Thanks A lot. it really helped

EstimatorsForte said...

Helped us too - thank you