Question by Ong:
Does P6 keep all the format (eg. level (this is most important), linkage, resources, cost etc) when export to Ms Project format?

Answer:
Yes, all the formats you mentioned will be exported to Project 2007, but you need to do some modification in the Advanced tab from the Task Information dialog box for some tasks; examples like deadline, constraints fields and/or constraint type...