1. Select the project you want to change the project start date in the
Project Workspace.
2. Select View, Show on Bottom, Project Details…
3. Click on the Dates tab: change the dates both in the
Planned Start and Data Date fields.
4. Open this project by right-clicking it in the Project workspace
and then select Open Project
5. Press F9 and check the date in the Current Data
Date field; make sure that the data date is the one just you have
changed.
6. Click on the Schedule button.