1. Select the project file in P6.
2. Select File > Export.
3. In the Export Format dialog box: select "Microsoft Project - XML 2007".
4. Click the Next button to open the Project to Export dialog box.
5. You can choose to save the file to the default location or change to other location.
6. Follow the instruction; click Next.. Next... Finish.
If you have doubt about this operation, email to kent@icpsprojects.com for advice.
Friday, July 31, 2009
Thursday, July 30, 2009
PRIMAVERA P6 TRAINING
Thw next training schedules in Primavera P6 will be conducted on 12-15 and 19-22 of August. Please register now for early confirmation. You may click this hyperlink to view the course outlines.
Wednesday, July 22, 2009
Earned Value Management Modules
Please be informed that the EVM modules using Primavera P6 will be conducted on 13-16 of August. If you are interested then request the registration form through kent 012-253 8283 or email to kent@icpsprojects.com for more information.
Tuesday, July 7, 2009
PRIMAVERA P6 TRAINING
Please be informed that the next training schedule for Primavera P6 will be conducted on 27-30 of July. You may call Kent 012-253 8283 or email to kent@icpsprojects.com to request the registration form.
Please visit the course modules to see the course outlines and other information.
Please visit the course modules to see the course outlines and other information.
Friday, June 19, 2009
Key Concept of Earned Value
Earned Value is a means for integrating Costs and Schedule. Earned Value refers to the determination of how much work has been performed on the basis of what was budgeted for the work that has actually been completed. The idea is that an owner has earned whatever amount was budgeted for the work that has in fact been completed. This value then becomes a measure against which other cost and schedule data can be compared in order to determine actual coast ans schedule status.
The earned value concept compares several measures to obtain an overall picture project status: BCWS, BCWP and ACWP. Comparing the BCWS and the ACWP values to the BCWP gives us an indication of variances from hte expected schedule variance and the cost variance.
If you are interested to get to the point to understand the concept of Varned Value and use it practically in your organization, then you can click this hyperlink to see the course modules. The proper tools is using P3 or P6 as suggested by Kent, the course facilitator.
The earned value concept compares several measures to obtain an overall picture project status: BCWS, BCWP and ACWP. Comparing the BCWS and the ACWP values to the BCWP gives us an indication of variances from hte expected schedule variance and the cost variance.
If you are interested to get to the point to understand the concept of Varned Value and use it practically in your organization, then you can click this hyperlink to see the course modules. The proper tools is using P3 or P6 as suggested by Kent, the course facilitator.
Saturday, June 13, 2009
Managing Your Projects Successfully
Learning Primavera or MS Project does not make you become an planning expert. In other word, learning how to manage your project in success using the proper tools is what your should go for. Kent Chan will assit you to become a planning expert.
First, you will be taught the concept of CPM before you start using the tools; secondly, you will be guided along by Kent to create a live project using either Primavera or MS Project from initial stage in planning and schedulng, through the usage of resources and costs, tracking the actual progress, and to managing the data and reports.
You can click this hyperlink to view the course modules and the personal profile of the course facilitator-Kent chan.
First, you will be taught the concept of CPM before you start using the tools; secondly, you will be guided along by Kent to create a live project using either Primavera or MS Project from initial stage in planning and schedulng, through the usage of resources and costs, tracking the actual progress, and to managing the data and reports.
You can click this hyperlink to view the course modules and the personal profile of the course facilitator-Kent chan.
Monday, May 18, 2009
Critical Path Scheduling Using Primavera P6
If you really want to understand the concept of Critical path method and using the proper tool in managing your projects, then choose this course to upgrade your career and prospect. Start your hands-on training on 03-06 of June.
You may click here to view the course module or call kent:012-253 8283 or email to kent@icpsprojects.com for more information.
You may click here to view the course module or call kent:012-253 8283 or email to kent@icpsprojects.com for more information.
Subscribe to:
Posts (Atom)